日本无限资源_福禄影院午夜伦_美国av毛片_亚洲自拍在线观看_激情亚洲一区国产精品_999久久久久

 
Feature: Uganda's new hydropower plant set to relieve power shortage, bridge skills transfer
                 Source: Xinhua | 2019-01-05 20:08:24 | Editor: huaxia

Chinese and Ugandan technicians work at the construction site of Isimba Power Plant Project in Kayunga district, Uganda, Aug. 8, 2017. As River Nile, the longest in the world, snakes through central Uganda, Chinese engineers and their local counterparts are constructing a multi-million U.S. dollar power plant on its bank in the remote Kayunga district. (Xinhua/Zhang Gaiping)

by Ronald Ssekandi, Zhang Gaiping

KAYUNGA, Uganda, Jan. 5 (Xinhua) -- Inside the power house at Isimba Hydropower Plant in the central Ugandan district of Kayunga, engineers subject the first unit of the plant to tests before the official commissioning slated for late January.

The engineers told Xinhua in a recent interview that after the commissioning of the first unit, they will move onto the second, third and eventually the fourth.

RELIEVING POWER SHORTAGE

The four units of the 183 MW Chinese constructed power plant would be commissioned in a phased manner, according to Xia Nenghai, General Manager of Uganda Branch, China International Water and Electric Corporation (CWE). CWE is the EPC contractor of the project.

Outside the power house, local workers under the supervision of Chinese technicians put final touches on the structural works.

"The civil work, the embankment of the dam, and the power house construction, the installation of the electric, mechanical equipment have been fully completed," said Xia.

The construction of the 568 million U.S. dollars power plant located on River Nile, the world's longest River, started in 2015, after Uganda secured a loan from China Export Import Bank. Uganda got the loan to address the country's power shortage, which economic experts said was stalling economic development.

After commissioning of all the units, the plant will generate the installed capacity of 183 MW, which is currently about 19 percent of the country's power generated. The country generates up to 974.84 MW, which experts say is inadequate and expensive.

When the Isimba power comes on to the national grid, it is expected to partly address the shortfall, according to the government.

Another Chinese funded Karuma Hydropower Plant is being constructed and is expected to generate 600 MW. The government anticipates that both the Isimba and Karuma power will address the country's power shortage.

SKILLS TRANSFER

At the construction site, the workforce has reduced as most of the structural works have been completed. What is now remaining is largely electrical and mechanical works, according to Xia.

At the peak of the construction, there were over 3,000 local workers ranging from semi-skilled to skilled.

Most of the youths who worked at the site gained more skills that they would use even after the project is long completed, according to Xia.

He said although the power plant is Chinese constructed, it has an American design as requested by the Ugandan government.

"We want to bring our Chinese knowledge, skills and management to the Ugandan people so that they can have more capability to work for their nation in future because we cannot stay here forever," Xia said.

"In future, Ugandans will build their country by themselves, with the correct skills," he added.

In communities neighboring the construction site, there is noticeable change as what was a small trading center has now expanded. Some of the workers from different parts of the country reside in the Busana trading center.

Xia said most of the employees were recruited from the community and surrounding districts, which explains the development in the area.

CWE also renovated a nearby school, Nakakandwa Primary School. The company, as part of its corporate social responsibility gave a new face-lift to the school.

Back to Top Close
Xinhuanet

Feature: Uganda's new hydropower plant set to relieve power shortage, bridge skills transfer

Source: Xinhua 2019-01-05 20:08:24

Chinese and Ugandan technicians work at the construction site of Isimba Power Plant Project in Kayunga district, Uganda, Aug. 8, 2017. As River Nile, the longest in the world, snakes through central Uganda, Chinese engineers and their local counterparts are constructing a multi-million U.S. dollar power plant on its bank in the remote Kayunga district. (Xinhua/Zhang Gaiping)

by Ronald Ssekandi, Zhang Gaiping

KAYUNGA, Uganda, Jan. 5 (Xinhua) -- Inside the power house at Isimba Hydropower Plant in the central Ugandan district of Kayunga, engineers subject the first unit of the plant to tests before the official commissioning slated for late January.

The engineers told Xinhua in a recent interview that after the commissioning of the first unit, they will move onto the second, third and eventually the fourth.

RELIEVING POWER SHORTAGE

The four units of the 183 MW Chinese constructed power plant would be commissioned in a phased manner, according to Xia Nenghai, General Manager of Uganda Branch, China International Water and Electric Corporation (CWE). CWE is the EPC contractor of the project.

Outside the power house, local workers under the supervision of Chinese technicians put final touches on the structural works.

"The civil work, the embankment of the dam, and the power house construction, the installation of the electric, mechanical equipment have been fully completed," said Xia.

The construction of the 568 million U.S. dollars power plant located on River Nile, the world's longest River, started in 2015, after Uganda secured a loan from China Export Import Bank. Uganda got the loan to address the country's power shortage, which economic experts said was stalling economic development.

After commissioning of all the units, the plant will generate the installed capacity of 183 MW, which is currently about 19 percent of the country's power generated. The country generates up to 974.84 MW, which experts say is inadequate and expensive.

When the Isimba power comes on to the national grid, it is expected to partly address the shortfall, according to the government.

Another Chinese funded Karuma Hydropower Plant is being constructed and is expected to generate 600 MW. The government anticipates that both the Isimba and Karuma power will address the country's power shortage.

SKILLS TRANSFER

At the construction site, the workforce has reduced as most of the structural works have been completed. What is now remaining is largely electrical and mechanical works, according to Xia.

At the peak of the construction, there were over 3,000 local workers ranging from semi-skilled to skilled.

Most of the youths who worked at the site gained more skills that they would use even after the project is long completed, according to Xia.

He said although the power plant is Chinese constructed, it has an American design as requested by the Ugandan government.

"We want to bring our Chinese knowledge, skills and management to the Ugandan people so that they can have more capability to work for their nation in future because we cannot stay here forever," Xia said.

"In future, Ugandans will build their country by themselves, with the correct skills," he added.

In communities neighboring the construction site, there is noticeable change as what was a small trading center has now expanded. Some of the workers from different parts of the country reside in the Busana trading center.

Xia said most of the employees were recruited from the community and surrounding districts, which explains the development in the area.

CWE also renovated a nearby school, Nakakandwa Primary School. The company, as part of its corporate social responsibility gave a new face-lift to the school.

010020070750000000000000011100001377220451
主站蜘蛛池模板: 成年美女黄网站色大免费全看 | 一区二区三区精品在线 | 国产AV尤物一区二区三区 | 精品欧美性 | 日本丰满大乳免费xxxx | 夜夜狂射影院欧美极品 | www.哥也色.com | 久久国产免费 | 欧美激情影音先锋 | 边摸边脱吃奶边高潮视频免费 | 91久久精品一区 | 日本xxxxxxxxx70hd 国内外成人在线视频 | 日日夜视频 | 亚洲日韩蜜桃av在线观看 | 最新中文字幕在线视频 | 爱情不设限在线观看 | 国产精品视频免费一区二区 | 99久久精品无免国产免费75 | 国产自无码视频在线观看 | 欧美日韩黄视频 | 免费在线观看视频完整 | 少妇被大黑捧猛烈进出A片 久久亚洲视频网 | 红色av社区 | 亚洲品质自拍视频 | 久久男人AV资源网站 | 中国一级毛片免费视频 | 久久久er热这里只有精品2 | 国产一级片每日更新 | 久久17| 日本熟妇无码色视频在线观看 | 性史性农村DVD毛片 97成人在线免费视频 | 蜜臀av网页 | 99在线精品免费视频九九视 | 久久不见久久见免费影院视频观看 | JK小仙女自慰流白浆呻吟 | 欧美又粗又长又爽做受 | www.久久综合 | 欧美人成在线视频 | 一区二区三区影视 | 草久在线观看 | 欧洲熟妇牲交 |